Construction Alerts

 

Date
9/11/2019



7/29/2019



7/29/2019


6/24/2019



5/10/2019

4/8/2019


4/2/2019

1/7/2019

10/5/2018

Notice
Phase 2 - Pavement Reconstruction
Roadway reconstruction within Phase 2 will begin on Saturday, September 12, 2019 between Allen Avenue and Hill Avenue

Phase 2 - Construction - South Side
Construction on the south side of Allen Avenue and Hill Avenue began Monday, July 29, 2019

Storm Drain Construction Begins
Storm drain construction began on Monday, July 29, 2019

Phase 2 - Construction - North Side
Construction between Allen Avenue and Hill Avenue is anticipated to begin on Monday, June 24, 2019

Phase 1 – Pavement Reconstruction
Roadway reconstruction within Phase 1 is anticipated to begin May 16 and last for approximately three weeks between Altadena Dr. and Allen Ave.

Phase 1 Construction - South Side
Construction began Monday, April 8, 2019 between Altadena Dr. and Allen Ave

Phase 1B – South Side
Curb, gutter, sidewalk construction, and more continues on the south side of New York Dr.

Phase 1 Construction Begins January 2019
Construction between Altadena Dr. and Allen Ave, will take place beginning January 2019. Road will be closed to through traffic. Local traffic access only.

Project Overview/ Tree Removal
Tree removal will began October 9, 2018. Trees will be replanted prior to project completion.